According to Taipower's latest announcement, in response to the practicality of field connection capabilities for the distribution-level renewable energy monitoring equipment test and management specifications, Taipower on 112/3/6 tested the inspection and statistics of return data every hour, every day tentatively. The official import of this process will be implemented on 112/7/3; please refer to the
linked file for details.
Practicality Statistics Importing Schedule
During the trial period (112/3/6-112/7/2)
- At 0:00 every morning, the system would conduct practical statistics.
- If the practicality of your site is lower than 95% after the statistics, the system will automatically send a notification to you for improvement.
- On the 1st of every month, a system notification letter will be sent to the sites where the overall practicality in the previous month did not reach 95%.
- During the trial period, there will be no penalties for sites with the practicality lower than 95%.
After the official implementation (after 112/7/2)
- At 0:00 every morning, the system will conduct practicality statistics.
- If the practicality of your site is lower than 95% after the statistics, the system will automatically send a notification to you for improvement.
- On the 1st of every month, a system notification letter will be sent to the sites where the overall practicality in the previous month was less than 95%.
- If the average practicality of this site is lower than 95% this month, Taipower will give a penalty according to the provisions of Article 13 of the power generation system power purchase agreement.
During the trial period, please ensure the following:
- Please confirm whether the series/parallel voltage on the application form corresponds to that on the voltage meter.
- Please confirm whether the power electrics information measured by the meter is normal.
- Please confirm whether the on-site gateway’s power supply, light signal, and network are normal.
What will BillionWatts do during the trial period?
BillionWatts would comprehensively check the practicality of DREAMS users’ sites and ensure that the site meets the specifications before the official implementation. If you have any questions, please contact BillionWatts Manager Liu at 0917-185-295.